Using the diagram you created in question 5, calculate ES,EF, LS, LF for each task and the

Question:

Using the diagram you created in question 5, calculate ES,EF, LS, LF for each task and the amount of slack. List the tasks that appear on the critical path.
In questions 5
Task A, duration 2, no dependency
Task B, duration 4, no dependency
Task C, duration 7, no dependency
Task D, duration 5, depends on Task A
Task E, duration 3, depends on Task B and Task C
Task F, duration 8, depends on Task C
Task G, duration 10, depends on Task D and Task E
Task H, duration 4, depends on Task E
Task I, duration 7, depends on Task F
Task J, duration 12, depends on Task H and Task I