Charlie Cook was able to determine the activity times for constructing his chemical contaminant tracking machine. Cook

Question:

Charlie Cook was able to determine the activity times for constructing his chemical contaminant tracking machine. Cook would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activitytimes:
Charlie Cook was able to determine the activity times for
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations management

ISBN: 978-0132163927

10th edition

Authors: Jay Heizer, Barry Render