Using the information given and expected project completion time from Problem 13(c), (a) Calculate the probability of

Question:

Using the information given and expected project completion time from Problem 13(c),

(a) Calculate the probability of completing the project in 36 weeks.

(b) Calculate the probability of completing the project in 40 weeks.