What is the probability that a project with the following precedence network will take more than 10

Question:

What is the probability that a project with the following precedence network will take more than 10 weeks to complete if the activity means and standard deviations (both in weeks) are as follows?
What is the probability that a project with the following
What is the probability that a project with the following
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management

ISBN: 978-0071091428

4th Canadian edition

Authors: William J Stevenson, Mehran Hojati

Question Posted: