You are the assistant project manager to Rassy Brown, who is in charge of the Nightingale project.
Question:
Rassy and her project team were developing a project plan aimed at producing 30 working models in time for MedCON, the biggest medical equipment trade show each year. Meeting the MedCON October 25 deadline was critical to success. All the major medical equipment manufacturers demonstrated and took orders for new products at MedCON. Rassy had also heard rumors that competitors were considering developing a similar product, and she knew that being first to market would have a significant sales advantage. Besides, top management made funding contingent upon developing a workable plan for meeting the MedCON deadline.
Use any project network computer program available to you to develop the schedule for activities noting late and early times, the critical path, and estimated completion for the project. Prepare a short memo that addresses the following questions:
1. Will the project as planned meet the October 25th deadline?
2. What activities lie on the critical path?
3. How sensitive is thisnetwork?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project management the managerial process
ISBN: 978-0073403342
5th edition
Authors: Eric W Larson, Clifford F. Gray
Question Posted: