A building contractor obtained bids for some asphalt paving, based on a specification. Three paving subcontractors quoted

Question:

A building contractor obtained bids for some asphalt paving, based on a specification. Three paving subcontractors quoted the following prices and ten of payment:
A building contractor obtained bids for some asphalt paving, based

The building contractor uses a 12% nomine interest rate, compounded monthly, in this type c bid analysis. Which paving subcontractor should b awarded the paving job?