A flexible manufacturing cell consists of a manual load/unload station, three CNC machines, and an automated guided
Question:
The FMC is used to machine four work parts. The product mix, routings, and processing times for the parts are presented in the table below:
The mean travel time of the AGVS between any two stations in the FMC is 3 min which includes the time required to transfer loads to and from the stations. Given that the loading on the system is maintained at 10 parts (10 work parts in the system at all times), use the extended bottleneck model to determine
(a) The bottleneck station,
(b) The production rate of the system and the average time to complete a unit of production, and
(c) The overall utilization of the system, not including the AGVS.