A mall with two levels is under construction. The plan is to install only 9 escalators at
Question:
• Option 1. Provide these facilities now for all 7 future escalators at $300,000.
• Option 2. Defer the investment in the facility as needed. Install 2 more escalators in two years, 3 more in five years, and the last 2 in eight years. The installation of these facilities at the time they are required is estimated to cost $140,000 in year 2, $160,000 in year 5, and $180,000 in year 8.
Additional annual expenses are estimated at $7,000 for each escalator facility installed. Assume that these costs begin one year subsequent to the actual addition. At an interest rate of 12%, compare the net present worth of each option over eight years.