A probabilistic network has a critical path of 21 days and a .95 probability of completing this
Question:
A probabilistic network has a critical path of 21 days and a .95 probability of completing this path in 24 days. Therefore, the project has a .95 chance of being finished by the end of the 24th day. True or False? Briefly explain your answer.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Answer rating: 75% (16 reviews)
False Only the path claimed to be critical has a 95 percent chance of being completed within ...View the full answer
Answered By
Anoop V
I have five years of experience in teaching and I have National Eligibility in teaching (UGC-NET) .
5.00+
1+ Reviews
10+ Question Solved
Related Book For
Project Management in Practice
ISBN: 978-0470533017
4th edition
Authors: Samuel J. Mantel Jr., Jack R. Meredith, Sco
Question Posted:
Students also viewed these Management Leadership questions
-
True or false Briefly explain in each case. a. Lenders in project financings rarely have any recourse against the projects owners if the project fails. b. Many new and exotic debt securities are...
-
A CPM/PERT project network has probabilistic activity times (x) as shown on each branch of the network; for example, activity 13 has a .40 probability that it will be completed in 6 weeks and a .60...
-
Answer true or false for below Exercises. If false, explain why. 1. It is possible to find the complement of a 120° angle. 2. The supplement of a 5° angle is a 175° angle. 3. Below is a...
-
Ava bought a house on 1 July 2000 for 62,000. She occupied the entire property as her PPR until 1 August 2007 when she began using one-quarter of the house for business purposes. This continued until...
-
How might moral intensity influence the decisions made by accounting professionals?
-
PURCHASES, PURCHASE RETURNS, AND PAYMENT FOR PURCHASES. Jordan Footwear sells athletic shoes. During April Jordan made the following purchases on credit with terms 3/15, n/40: lol Assume that Jordan...
-
Phishing is an industry-wide problem. Organizations may better be able to solve phishing problems or mitigate their consequences by working together. a. Name and describe three specific industry...
-
Engineering design is an activity that is vital to the success of any motor vehicle manufacturer. Identify the level at which engineering design would be classified in the cost hierarchy used with...
-
The following data apply to Pro Beauty Supply Incorporated for May, Year 2 : Balance per the bank on May 3 1 , $ 1 1 , 1 0 0 . Deposits in transit not recorded by the bank, $ 1 , 9 0 0 . Bank error,...
-
X Ltd. has 10 lakhs equity shares outstanding at the beginning of the accounting year 2016. The appropriate P/E ratio for the industry in which D Ltd. is 8.35. The earnings per share is Rs. 15 in the...
-
When using AON networks, how does one indicate an event such as a project milestone?
-
Not uncommonly, the Gantt chart is deceptive in its apparent simplicity. Briefly explain.
-
a. Evaluate x ln x 2 dx using the substitution u = x 2 and evaluating ln u du. b. Evaluate x ln x 2 dx using integration by parts. c. Verify that your answers to parts (a) and (b) are consistent.
-
Begin by locating a scholarly article regarding the effects of increases on minimum wages and discuss its findings. Does a minimum wage increase lead to reductions in employment, or is the overall...
-
Pick an organization (or you can use an example that has professional relevance), and use the DAC framework to accomplish the following objectives. Provide background and a problem statement of the...
-
Woodruff Company is currently producing a snowmobile that uses five specialized parts. Engineering has proposed replacing these specialized parts with commodity parts, which will cost less and can be...
-
What was Newell's organizational culture like before acquiring Rubbermaid? What was the quadrant? Is the perspective short or long term, inside or outside focused, interested in people, process, or...
-
(7.47 of Koretsky 2nd edition) A binary mixture of species 1 and 2 can be described by the following equation of state: P = a 0 VoT The pure species coefficients are given by: amix y1a1a2Y2 with the...
-
From the following selected data, compute:1. Net cash flow provided (used) by operating activities.2. Net cash flow provided (used) by investing activities.3. Net cash flow provided (used) by...
-
Suppose that you are part of a virtual team and must persuade other team members on an important matter (such as switching suppliers or altering the project deadline). Assuming that you cannot visit...
-
For each of the following differential equations write down the differential operator L that would enable the equation to be expressed as L[x(t)] = 0: dx (a) = f(t)x dt (b) (c) (e) 60 dx dt (h) dx dt...
-
A sales project at month 5 had an actual cost of $34,000, a planned cost of $42,000, and a value completed of $39,000. Find the cost and schedule variances and the CPI and SPI.
-
A software development project at day 70 exhibits an actual cost of $78,000 and a scheduled cost of $84,000. The software manager estimates a value completed of $81,000. What are the cost and...
-
A project to develop a county park has an actual cost in month 17 of $350,000, a planned cost of $475,000, and a value completed of $300,000. Find the cost and schedule variances and the three...
-
Accounting changes fall into one of three categories. Identify and explain these categories and give an example of each one.
-
Machinery is purchased on May 15, 2015 for $120,000 with a $10,000 salvage value and a five year life. The half year convention is followed. What method of depreciation will give the highest amount...
-
Flint Corporation was organized on January 1, 2020. It is authorized to issue 14,000 shares of 8%, $100 par value preferred stock, and 514,000 shares of no-par common stock with a stated value of $2...
Study smarter with the SolutionInn App