After consulting with Butch Radner, George Monohan was able to determine the activity times for constructing the
Question:
ACTIVITY TIME (WEEKS)
A .......... 6
B .......... 5
C .......... 3
D .......... 2
E .......... 4
F .......... 6
G .......... 10
H .......... 7