Alpine Bicycle Company manufactures mountain bikes. The following data for May of the current year are available:

Question:

Alpine Bicycle Company manufactures mountain bikes. The following data for May of the current year are available:

Quantity of direct labor used …………..… 600 hrs.

Actual rate for direct labor ………....... $12.50 per hr.

Bicycles completed in May …………………. 280

Standard direct labor per bicycle ……….….. 2 hrs.

Standard rate for direct labor …..…… $12.75 per hr.

Planned bicycles for May …………………….310

Determine the direct labor rate and time variances.