Alpine Bicycle Company manufactures mountain bikes. The following data for May of the current year are available:
Question:
Alpine Bicycle Company manufactures mountain bikes. The following data for May of the current year are available:
Quantity of direct labor used …………..… 600 hrs.
Actual rate for direct labor ………....... $12.50 per hr.
Bicycles completed in May …………………. 280
Standard direct labor per bicycle ……….….. 2 hrs.
Standard rate for direct labor …..…… $12.75 per hr.
Planned bicycles for May …………………….310
Determine the direct labor rate and time variances.