Question: An electrical contractor is examining the amount of time his crews take to complete wiring jobs. Some crews seem to take longer than others. For
An electrical contractor is examining the amount of time his crews take to complete wiring jobs. Some crews seem to take longer than others. For an upcoming job, a list of activities and their optimistic, most likely, and pessimistic completion times are given in the following table.
.png)
(a) Develop a project network for this problem.
(b) Determine the expected duration and variance for each activity.
(c) Determine the EST, EFT, LST, LFT, and slack for each activity. Also determine the total project completion time and critical path(s) for installing electrical wiring and equipment.
(d) What is the probability that this job will finish in 38 days or less?
DAYS IMMEDIATE b PREDECESSORS ACTIVITY B, D A, E A, E 10 10 12 H, I
Step by Step Solution
3.34 Rating (172 Votes )
There are 3 Steps involved in it
tr msoheightsourceauto col msowidthsourceauto br msodataplacementsamecell style0 msonumberformatGeneral textaligngeneral verticalalignbottom whitespacenowrap msorotate0 msobackgroundsourceauto msopatt... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
718-M-S-L-P (1175).xlsx
300 KBs Excel File
