An electrical contractor is examining the amount of time his crews take to complete wiring jobs. Some
Question:
(a) Develop a project network for this problem.
(b) Determine the expected duration and variance for each activity.
(c) Determine the EST, EFT, LST, LFT, and slack for each activity. Also determine the total project completion time and critical path(s) for installing electrical wiring and equipment.
(d) What is the probability that this job will finish in 38 days or less?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Managerial Decision Modeling With Spreadsheets
ISBN: 718
3rd Edition
Authors: Nagraj Balakrishnan, Barry Render, Jr. Ralph M. Stair
Question Posted: