At the end of June the manager of the B.C. manufacturing plant was provided with the following

Question:

At the end of June the manager of the B.C. manufacturing plant was provided with the following variance analysis report.

At the end of June the manager of the B.C.

The manager immediately called the production supervisor, demanding an explanation for the large unfavourable variance for the quarter. The production supervisor was puzzled. He thought the cost- cutting measures they had incorporated were beginning to work. He certainly wasn't expecting such a large discrepancy.
The budget that was created in Chapter 10 was used to establish the standard rates the plant was using with its normal costing system. They are summarized below.

At the end of June the manager of the B.C.

Other relevant information:
1. A total of 400,000 kg of direct materials were purchased during the quarter at a cost of $1.55 per kilogram.
2. A total of 380,990 kg of direct materials were used in production to manufacture 357,000 units.
3. Payroll recorded 88,325 direct labour hours at an average cost of $17.80 per hour.
Instructions
Do you agree with the plant manager that the production supervisor performed poorly, as might be indicated by the large unfavourable variance? Explain fully. Include in your response calculations of all production variances.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Managerial Accounting Tools for Business Decision Making

ISBN: 978-1118856994

4th Canadian edition

Authors: Jerry J. Weygandt, Paul D. Kimmel, Donald E. Kieso, Ibrahim M. Aly

Question Posted: