Beaty Construction Company decided at the beginning of 2008 to change from the completed-contract method to the

Question:

Beaty Construction Company decided at the beginning of 2008 to change from the completed-contract method to the percentage-of-completion method for financial reporting purposes. The company will continue to use the completed-contract method for tax purposes. For years prior to 2008, pre-tax income under the two methods was as follows: percentage-of-completion $128,000, and completed-contract $80,000. The tax rate is 35%. Prepare Beaty’s 2008 journal entry to record the change in accounting principle.