Consider Table 6-2, Network Diagram Data for a Small Project. All duration estimates or estimated times are
Question:
Consider Table 6-2, Network Diagram Data for a Small Project. All duration estimates or estimated times are in days; and the network proceeds from Node 1 to Node 9.
a. Draw an ADA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time.
b. Identify all of the paths on the network diagram and note how long they are, using figure as a guide for how to represent each path.
c. What is the critical path for this project and how long is it?
d. What is the shortest possible time it will take to complete thisproject?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Question Posted: