Consider Table 6-3, Network Diagram Data for a Large Project. All duration estimates or estimated times are in weeks; and the network proceeds from Node 1 to Node 8.

Consider Table 6-3, Network Diagram Data for a Large Project.

a. Draw an AOA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time.
b. Identify all of the paths on the network diagram and note how long they am, using figure as a guide for how to represent each path.
c. What is the critical path for this project and how long is it?
d. What is the shortest possible time it will take to complete thisproject?