Question: Cost elements associated with the operation of the ten-station transfer line in Problem 16.4 are as follows: raw work part cost = $0.55/pc, line operating

Cost elements associated with the operation of the ten-station transfer line in Problem 16.4 are as follows: raw work part cost = $0.55/pc, line operating cost = $42.00/hr, and cost of disposable tooling = $0.27/pc. Compute the average cost of a work piece produced.
Problem 16.4
A ten-station transfer machine has an ideal cycle time of 30 sec. The frequency of line stops is 0.075 stops per cycle. When a line stop occurs, the average downtime is 4.0 min.

Step by Step Solution

3.39 Rating (177 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Refers to Pro... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

795-C-S-A-I (699).docx

120 KBs Word File

Students Have Also Explored These Related Artificial Intelligence Questions!