Dash Company adopted a standard costing system several years ago. The standard costs for the prime costs

Question:

Dash Company adopted a standard costing system several years ago. The standard costs for the prime costs (i.e., direct materials + direct labor) of its single product are


All materials are added at the beginning of processing. The following data were taken from the company’s records for November:

In-process beginning inventory ......none

In-process ending inventory ........800 Units, 75 percent complete as to labor

Units completed ...........5,600 Units

Budgeted output...........6,000 Units

Purchases of materials ........50,000 Kilograms

Total actual labor costs ........$600,000

Actual hours of labor .........36,500 Hours

Materials usage variance.......$1,500 Unfavorable

Total materials variance...........$750 Unfavorable

Required

1. Compute for November:

a. The labor efficiency variance.

b. The labor rate variance.

c. The actual number of kilograms of material used in the production process during the month.

d. The actual price paid per kilogram of material during the month.

e. The total amounts of material and labor cost transferred to the finished goods account.

f. The total amount of material and labor cost in the work-in-process inventory account at the end of November.

2. Prepare journal entries to record all transactions including the variances in requirement 1.

Ending Inventory
The ending inventory is the amount of inventory that a business is required to present on its balance sheet. It can be calculated using the ending inventory formula                Ending Inventory Formula =...
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer: