Question: Development of Version 2.0 of a particular accounting software product is being considered by Jose Nogueras technology firm in Baton Rouge. The activities necessary for

Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera€™s technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table:

Development of Version 2.0 of a particular accounting software product

a) What is the project completion date?
b) What is the total cost required for completing this project on normal time?
c) If you wish to reduce the time required to complete this project by 1 week, which activity should be crashed, and how much will this increase the total cost?
d) What is the maximum time that can be crashed? How much would costsincrease?

NORMALI CRASH TIME | TIME NORMAL RASH! IMMEDIATE ACTVITY WEEKS) (WEEKS) COST COST PREDECESSons 2,000 2,600 2,200 2,800 500 500 2,300 2,600 900 1,200 3,000 4,200 1,400 2,000

Step by Step Solution

3.31 Rating (160 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Project completion time 16 Activities ADG Activity Norm Time Cr... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

286-B-M-L-O-M (2416).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!