Question: Development of Version 2.0 of a particular accounting software product is being considered by Jose Nogueras technology firm in Baton Rouge. The activities necessary for
.png)
a) What is the project completion date?
b) What is the total cost required for completing this project on normal time?
c) If you wish to reduce the time required to complete this project by 1 week, which activity should be crashed, and how much will this increase the total cost?
d) What is the maximum time that can be crashed? How much would costsincrease?
NORMALI CRASH TIME | TIME NORMAL RASH! IMMEDIATE ACTVITY WEEKS) (WEEKS) COST COST PREDECESSons 2,000 2,600 2,200 2,800 500 500 2,300 2,600 900 1,200 3,000 4,200 1,400 2,000