During the last 6 weeks, the actual costs of labor for Solsana Company were as follows: Week
Question:
During the last 6 weeks, the actual costs of labor for Solsana Company were as follows:
Week 1...........$38,500...........Week 4...........$45,600
Week 2...........$40,000...........Week 5...........$48,000
Week 3...........$42,000...........Week 6...........$51,000
The standard materials cost for each week was $40,000 with an allowable deviation of ±5,000.
Required:
Plot the actual costs over time against the upper and lower limits. Comment on whether or not there is a need to investigate any of the variances.