During the last 6 weeks, the actual costs of materials for Brennen Company were as follows:
Week 1.............$57,600.............Week 4.............$68,400
Week 2.............$60,000.............Week 5.............$69,000
Week 3.............$63,000.............Week 6.............$69,500
The standard materials cost for each week was $60,000 with an allowable deviation of ±6,000.
Required:
Plot the actual costs over time against the upper and lower limits. Comment on whether or not there is a need to investigate any of the variances.