During year 1, Meriwether Construction Company started a construction job with a contract price of $ 3,000,000.

Question:

During year 1, Meriwether Construction Company started a construction job with a contract price of $ 3,000,000. The job was completed in year 2 and the company uses the percentage of completion method. The following information is available for year 1 and year 2:
During year 1, Meriwether Construction Company started a construction job

What amount of gross profit should Meriwether recognize for this job for year 2?
a. $ 250,000
b. $ 1,000,000
c. $ 350,000
d. $ 600,000