Question: Five jobs are waiting to be run. Their expected run times are 9, 6, 3, 5, and X. In what order should they be run
Five jobs are waiting to be run. Their expected run times are 9, 6, 3, 5, and X. In what order should they be run to minimize average response time?
Step by Step Solution
3.41 Rating (167 Votes )
There are 3 Steps involved in it
Shortest job first is the way ... View full answer