In a two-bin inventory system, the demand for three- inch lag bolts during the two-week lead time

Question:

In a two-bin inventory system, the demand for three- inch lag bolts during the two-week lead time is normally distributed, with an average of 53 units per week. The standard deviation of weekly demand is 5 units. What cycle-service level is provided when the normal level in the second bin is set at 120 units?