In a continuous review inventory system, the lead time for door knobs is five weeks. The standard

Question:

In a continuous review inventory system, the lead time for door knobs is five weeks. The standard deviation of demand during the lead time is 85 units. The desired cycle-service level is 99 percent. The supplier of door knobs streamlined its operations and now quotes a one- week lead rime how much can safety stock be reduced without reducing the 99 percent cycle, service level?