Lancaster Metals has the following average times (in hours): Transporting product. . . . . . .

Question:

Lancaster Metals has the following average times (in hours):
Transporting product. . . . . . . . . 0.25
Manufacturing product . . . . . . . 1.00
Inspecting product . . . . . . . . . . 0.25
Storing inventory . . . . . . . . . . . 2.50
Required
Calculate the manufacturing cycle efficiency.