Mary is planning her wedding and develops the following preliminary information. a. Draw the network for this

Question:

Mary is planning her wedding and develops the following preliminary information.

Mary is planning her wedding and develops the following preliminary

a. Draw the network for this project.
b. What is the critical path(s)?
c. What is the project completion time?
d. What activity has the most slack?
e. What wedding activities did Mary leave out of her analysis? List them and now redraw the project network (but do NOT try to assign activity times or work out the new solution). What did you learn?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

OM6 operations supply chain management

ISBN: 978-1305664791

6th edition

Authors: David Alan Collier, James R. Evans

Question Posted: