Mission Oak Company produces oak bookcases to customer order. It received an order from a customer to
Question:
Process time . . . . . . . . . 18.0 days
Inspection time . . . . . . . 2.0 days
Move time . . . . . . . . . . . 4.4 days
Wait time . . . . . . . . . . . 20.6 days
Required
1. Compute the company’s manufacturing cycle time.
2. Compute the company’s manufacturing cycle efficiency. Interpret your answer.
Analysis Component
3. Assume that Mission Oak wishes to increase its manufacturing cycle efficiency to 0.75. What are some ways that it can accomplish this?