On March 1, 2012, Avengers Construction Company contracted to construct a factory building for Marvel Manufacturing Inc.
Question:
On March 1, 2012, Avengers Construction Company contracted to construct a factory building for Marvel Manufacturing Inc. for a total contract price of $6,500,000. The building was completed by October 31, 2014. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Marvel for 2012, 2013, and 2014 are given below.
a. Assume Marvel uses the percentage of completion method.
b. Assume Avengers uses the completed contractmethod.