On March 1, 2014, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc.

Question:

On March 1, 2014, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The building was completed by October 31, 2016. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2014, 2015, and 2016 are given below.
2014 2015 2016 Contract costs incurred during the year Estimated costs to complete the contract at 12/31 Billings to Fab

Instructions
(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2014, 2015, and 2016. (Ignore income taxes.)
(b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2014, 2015, and 2016. (Ignore incomes taxes.)

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Intermediate Accounting 2014 FASB Update

ISBN: 978-1118147290

15th edition

Authors: Donald E. Kieso, Jerry J. Weygandt, Terry D. Warfield

Question Posted: