One operator services a group of five machines. Machine run time and service durations are both Exponential.

Question:

One operator services a group of five machines. Machine run time and service durations are both Exponential. Machines run for an average of 90 minutes after a service, and service duration averages 35 minutes. The operator receives $20 per horn- in wage and fringe benefits, and machine downtime costs $70 per hour per machine.
a. If each machine produces 60 piece s per hour while running, find the average hour Iv output of each machine when waiting and service times are taken into account.
b. Determine the optimum number of operators.
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management

ISBN: 978-0071091428

4th Canadian edition

Authors: William J Stevenson, Mehran Hojati

Question Posted: