Robyn Cucurullo is developing a social networking app for tablet computers. She has the following stages completed
Question:
a. Create a table similar to the one in Figure 3.27.
b. For Week 3, calculate the budget at completion (BAC), planned value (PV), actual cost (AC), and earned value (EV) at Week 3.
c. For Week 3, calculate the performance measures of cost variance (CV), schedule variance (SV), the cost performance index (CPI), and the schedule performance index (SPI).
d. What can you tell about the budget in Week 3 by using these performance measures?
e. What can you tell about the schedule in Week 3 by using these performance measures?
f. For Week 3, calculate the estimated time to complete (ETC) and estimate at completion (EAC).
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Systems Analysis and Design
ISBN: 978-0133023442
9th edition
Authors: Kenneth E. Kendall, Julie E. Kendall
Question Posted: