Rose is a project manager at the civil engineering consulting firm of Sands, Gravel, Concrete, and Waters,

Question:

Rose is a project manager at the civil engineering consulting firm of Sands, Gravel, Concrete, and Waters, Inc. She has been collecting data on a project in which concrete pillars were being constructed, however not all the data are available. She has been able to find out that the 10th pillar required 260 person-hours to construct, and that a 75% learning curve applied. She is interested in calculating the time required to construct the 15tand 20th pillars. Compute the values for her.
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Engineering Economic Analysis

ISBN: 9780195168075

9th Edition

Authors: Donald Newnan, Ted Eschanbach, Jerome Lavelle

Question Posted: