The following table provides the crash data for the network project described in Problem 6: Activity Time
Question:
The following table provides the crash data for the network project described in Problem 6:
Activity Time (months) Activity Cost ($1,000s)
Activity Normal Crash Normal Crash 1 8 5 $ 700 $1,200 2 10 9 1,600 2,000 3 9 7 900 1,500 4 4 2 500 700 5 6 3 500 900 6 5 4 500 800 7 7 5 700 1,000 8 15 12 1,400 2,000 9 12 10 1,800 2,300 10 18 14 1,400 3,200 11 4 3 500 800 12 7 6 800 1,400 Using the computer, crash the network to 32 months. Indicate the first critical path activities and then the cost of crashing the network. LO.1