The following table provides the crash data for the network project described in Problem 6: Activity Time

Question:

The following table provides the crash data for the network project described in Problem 6:

Activity Time (months) Activity Cost ($1,000s)

Activity Normal Crash Normal Crash 1 8 5 $ 700 $1,200 2 10 9 1,600 2,000 3 9 7 900 1,500 4 4 2 500 700 5 6 3 500 900 6 5 4 500 800 7 7 5 700 1,000 8 15 12 1,400 2,000 9 12 10 1,800 2,300 10 18 14 1,400 3,200 11 4 3 500 800 12 7 6 800 1,400 Using the computer, crash the network to 32 months. Indicate the first critical path activities and then the cost of crashing the network. LO.1

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: