Question: Construct a Gantt chart for the general multipurpose plant in Figure 22.14, but with the unit assignments specified in Figure 22.13. Figure 22.13:- Figure 22.14:-
Construct a Gantt chart for the general multipurpose plant in Figure 22.14, but with the unit assignments specified in Figure 22.13.
Figure 22.13:-

Figure 22.14:-

Product A Product B Task 1 Task 2 Task 1 Task 2 Batch Time, hr Unit 4 6 5 4 U1 U2, U3 U1, U2 U3 Product A Day 1 Day 2 U1 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 U2 U3 Product B Day 1 8 9 10 11 12 1 2 3 4 5 6 U1 U2 U3 Cycle Time = 4 hr Day 2 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 Cycle Time = 4 hr Figure 22.13 Gantt charts for a multipurpose plant.