How would your answers differ to Exercise 5 if this were an open-book negotiated project with a

Question:

How would your answers differ to Exercise 5 if this were an open-book negotiated project with a 75–25% savings split favoring the project owner?

Data from exercise 5

Utilizing the buyout log developed in Exercise 1, if the project was to finish with exactly those buyout values equaling as-built costs, and all other estimated costs were to equal actual costs (which is unlikely), prepare a fee forecast for the project. What would the final fee for City Construction Company be? Would the owner realize any project savings? How would those savings be reflected in the final contract amount?

Data from exercise 1

Assume the following buyout values for the case study project. Begin with the final bid estimate developed in Chapter 20 and develop a buyout log similar to Figure 24.2. You will have to look at examples presented earlier in the book and make a few derivations and assumptions to complete this exercise.

Figure 24.2

Project: Carpenter's Training Center Spec Section Description 050000 Supply Steel 074000 Roof and Flashing

Buy reinforcement steel:  Install structural steel and metal deck:  Landscaping and irrigation:  Unit price

Storefront, excluding purchase of punch windows:  Elevators, including cab upgrades: $3.2 million $1.2 million

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Construction Cost Estimating

ISBN: 9780367902681

1st Edition

Authors: John E. Schaufelberger, Len Holm

Question Posted: