Revise the lump sum schedule of values (as shown in the far-right column of Figure 24.3) by

Question:

Revise the lump sum schedule of values (as shown in the far-right column of Figure 24.3) by front-end loading all the fee and general conditions and other markups to the areas of self-performed general contractor work. This is exclusive of Exercise 1.

Figure 24.3

Project: Carpenters Training Center CSI Division 1 2345 6 7 8 9 10 11 12 13 14 15 21 22 23 26 31 Columns:

Data from exercise 1

Assume the following buyout values for the case study project. Begin with the final bid estimate developed in Chapter 20 and develop a buyout log similar to Figure 24.2. You will have to look at examples presented earlier in the book and make a few derivations and assumptions to complete this exercise.

Figure 24.2

City Construction Company Buyout Log Project: Carpenter's Training Center Spec Section Description 050000

Buy reinforcement steel:  Install structural steel and metal deck:  Landscaping and irrigation:  Unit price

Storefront, excluding purchase of punch windows:  Elevators, including cab upgrades: $3.2 million $1.2 million

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Construction Cost Estimating

ISBN: 9780367902681

1st Edition

Authors: John E. Schaufelberger, Len Holm

Question Posted: