Revise the lump sum schedule of values (as shown in the right column of Figure 24.3) by
Question:
Revise the lump sum schedule of values (as shown in the right column of Figure 24.3) by combining items to create a l0 line-item schedule of values. This is exclusive of Exercise 1.
Figure 24.3
Data from exercise 1
Assume the following buyout values for the case study project. Begin with the final bid estimate developed in Chapter 20 and develop a buyout log similar to Figure 24.2. You will have to look at examples presented earlier in the book and make a few derivations and assumptions to complete this exercise.
Figure 24.2
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Construction Cost Estimating
ISBN: 9780367902681
1st Edition
Authors: John E. Schaufelberger, Len Holm
Question Posted: