The contractor installing the sewer pipe in Figures 16.3 and 16.4 chose a moveable trench shoring system

Question:

The contractor installing the sewer pipe in Figures 16.3 and 16.4 chose a moveable trench shoring system over a 1:1 slope cut excavation.

Figure 16.3

Tri-County Conveyance Pipeline - Estimate Bid Item: 4- Install 18" PVC Sanitary Sewer Quantity Description

Figure 16.4

1 1 10' across Shoring box option 2' 18" -2' <5'-5" at bottom > 25'-5" at top Conventional slope-cut

Calculate the contractor’s overall savings for this approach utilizing the excavation conversion process and pricing discussed with structural excavation in Chapters 6 and 10. Assume the native soils are sufficient for backfill.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Construction Cost Estimating

ISBN: 9780367902681

1st Edition

Authors: John E. Schaufelberger, Len Holm

Question Posted: