Why should the estimator stay with the concrete pump cost of $15/CY already included in the direct

Question:

Why should the estimator stay with the concrete pump cost of $15/CY already included in the direct work estimate and not modify concrete costs with the concrete pump quote (Figure 13.2) received on bid day?

Figure 13.2

A 105-foot boom pump is to be used to pump 100 CY of concrete in 4 hours (HR). What is the estimated cost per