8. Courts will normally enforce a liquidated damages clause if the daily amount is a reasonable prediction

Question:

8. Courts will normally enforce a liquidated damages clause if the daily amount is a reasonable prediction of the damages that an owner might suffer. In a liquidated damage clause, the parties agree in advance to the daily amount payable to the owner in the case of contractor- caused delay. True or false?