A new road section with concrete pavement, shown in longitudinal section, is 11,600 feet long. It is

Question:

A new road section with concrete pavement, shown in longitudinal section, is 11,600 feet long. It is to be constructed in accordance with the following conditions:

The balanced earthworks from station 00 to 58(00) may be done at the same time as the balanced earthworks from station 58(00) to 116(00) using two separate independent crews.

The double-box culvert will be built by one crew, and another crew will build the two small culverts. Concrete may be supplied either from the paving batch plant or from small independent mixers at the culvert sites, whichever is expedient.

One small slip-form paver will do all the concrete paving work, and all the shouldering will then follow with one crew after the concrete pavement is cured.

Seeding the embankments with grass must be left as late as possible.

Prepare a network diagram and determine the minimum possible project duration.

If independent concrete mixers are used for the culverts, what is the latest day for delivery of the paving batch plant to the site, so that the paving crew may have continuity of work (no idle time at all)?

image text in transcribed

image text in transcribed

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Construction Management

ISBN: 9780470447239

4th Edition

Authors: Daniel W. Halpin, Bolivar A. Senior

Question Posted: