Make a clear and neat sketch of the network specified below using precedence notation. On the precedence
Question:
Make a clear and neat sketch of the network specified below using precedence notation. On the precedence diagram calculate and showthe early start (EST), early finish (EFT), late start (LST), late finish (LFT), and TF in each activity. Start calculations with day zero 0. Show the critical paths with colored pencil.
Step by Step Answer:
Related Book For
Construction Management
ISBN: 9780470447239
4th Edition
Authors: Daniel W. Halpin, Bolivar A. Senior
Question Posted: