Calculate the takt time for a production project that calls for the production of 125 units of

Question:

Calculate the takt time for a production project that calls for the production of 125 units of a product within an 8 -h workday that includes two \(15-\mathrm{min}\) rest breaks and a \(45-\)-min lunch break.