Develop a general LP formulation for scheduling the project in Table 7.12. Resource requirements and precedence relationships
Question:
Develop a general LP formulation for scheduling the project in Table 7.12. Resource requirements and precedence relationships must be satisfied in the model \(\left(R_{1}=5, R_{2}=3\right)\).
Table 7.12