For the project data in Exercise 4.20, assume that the given activity durations represent the most likely
Question:
For the project data in Exercise 4.20, assume that the given activity durations represent the most likely PERT estimates \((m)\). Define the other PERT estimates \(a\) and \(b\) as follows:
\[ \begin{aligned} & a=m-1 \\ & b=m+1 \end{aligned} \]
Disregarding the PDM lead-lag constraints, find the probability of finishing the project within 51 time units.
Exercise 4.20
Assume that we have the following precedence diagramming network data:
The following PDM restrictions are applicable to the network:
\[ \begin{aligned} & \mathrm{SS}_{\mathrm{AB}}=3 \\ & \mathrm{FF}_{\mathrm{AB}}=12 \\ & \mathrm{FS}_{\mathrm{BC}}=1 \\ & \mathrm{SS}_{\mathrm{BD}}=6 \\ & \mathrm{SF}_{\mathrm{DE}}=13 \\ & \mathrm{FS}_{\mathrm{FG}}=3 \end{aligned} \]
If the project start time is \(t=5\) and the project due date is \(t=52\), perform conventional CPM analysis of the network without considering the lead-lag PDM restrictions. Show both forward and backward passes. Identify the critical path. Tabulate the TS and FS for the activities in the network.
Step by Step Answer:
Project Management Systems Principles And Applications
ISBN: 272859
2nd Edition
Authors: Adedeji B. Badiru