Assume that we have the following precedence diagramming network data: The following PDM restrictions are applicable to

Question:

Assume that we have the following precedence diagramming network data:

image text in transcribed

The following PDM restrictions are applicable to the network:

\[ \begin{aligned} & \mathrm{SS}_{\mathrm{AB}}=3 \\ & \mathrm{FF}_{\mathrm{AB}}=12 \\ & \mathrm{FS}_{\mathrm{BC}}=1 \\ & \mathrm{SS}_{\mathrm{BD}}=6 \\ & \mathrm{SF}_{\mathrm{DE}}=13 \\ & \mathrm{FS}_{\mathrm{FG}}=3 \end{aligned} \]
If the project start time is \(t=5\) and the project due date is \(t=52\), perform conventional CPM analysis of the network without considering the lead-lag PDM restrictions. Show both forward and backward passes. Identify the critical path. Tabulate the TS and FS for the activities in the network.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: