List the common causes of changed conditions in a building contract. What typical contract clauses bear on

Question:

List the common causes of changed conditions in a building contract. What typical contract clauses bear on the problems caused by changed conditions? Suppose separate contracts are let for the building foundations and all remaining work. If you are the second contractor and you find that the foundations are incorrectly located, either in plan or elevation, would you be able to claim a changed condition?