Presented in the table is the activity data for a project that is subject to variable resource
Question:
Presented in the table is the activity data for a project that is subject to variable resource availability. It is assumed that the scaled CAF weights for the activities are already known, as given in the last column of the tabulated data. There are two resource types. Resource availability varies from day to day on the basis of the RS tabulated after the project data.
Variable resource availability for the project is as follows:
Use the CAF weights to develop the Gantt chart for the project considering the daily resource availability. A task that is already in progress will be temporarily suspended whenever there are not enough units of resources to continue it. The task will resume (without increasing its duration) whenever enough resources become available.