Use the minimum totals lack (Min TS) heuristic to schedule the resource-constrained project. If a tie occurs,

Question:

Use the minimum totals lack (Min TS) heuristic to schedule the resource-constrained project. If a tie occurs, use minimum activity duration to break the tie.

Units of resource type 1 available \(=10\)

Units of resource type 2 available \(=15\)